Pump Protection & turbine Burrawang pumping station 24MW
Problem: Hi silica levels-& Algae, damage to 5MW pumps & glands
Solution: Fully automatic backwashing Eliminator Strainer Special fabricated skid and Variable Speed Pumps, Achieved non stop running
Client: Burrawang Pumping Station, NSW. 2006 & 2007